| HOME > CONSTRUCTION > Project: Adak Upgrades | ||
|
||
|
News | Jobs | Staff Directory | Contact Us | |
![]() Representative Project: Adak Upgrades
Client: Federal Aviation Administration, Alaska Region
Primary objectives for the project were:
The upgrades were completed in three phases. During Phase I, FAA, Bristol and subcontractor personnel visited the Adak site to observe existing conditions and discuss needed upgrades. In Phase 2, BCS provided designs, a construction cost estimate and a schedule for completing upgrades. Phase three involved implenting the upgrades. Bristol Construction Services improved upon the FAA’s original plan, which had been to move and refurbish a 40-foot tower from Yakutat for use in Adak. Alternatively, BCS recommended installing new telescoping antenna masts to support UHF and VHF antennas in each of the two SACOM radomes.
Bristol Construction’s approach:
The FAA accepted these recommendations in early July 2005 and tasked Bristol with providing designs for radio frequency and power cabling, trenching, cabinets, surge suppressor installation, grounding, SACOM radome penetrations and telescoping antenna mast installation. BCS and subcontractors participated in two design charettes with the FAA during July in order to fast-track the design review and acceptance. The notice-to-proceed came in mid-August 2005. Because fall weather in the Aleutians is notoriously poor and can drive up construction costs, BCS planned the construction schedule around a completion date of no later than September 30, 2005. Adak is only accessible by water or air. Bristol Construction charted a Hercules C-130 cargo plane to deliver 43,000 pounds of materials and construction support equipment to Adak September on September 5. A seven-person field crew worked 12 hours a day, seven days a week — performing work inside on days when weather was poor — and essentially completed all upgrades by September 28. Joint Acceptance Inspections held on the emergency generator fuel supply and SACOM upgrades found no major exceptions to the work. The crew completed demobilization activities and departed Adak on September 29. Throughout fieldwork, FAA personnel in Anchorage and on Adak Island worked closely with BCS to answer questions and provide technical guidance— a close working relationship that was instrumental to completing the project on schedule.
PROJECT ACTIVITIES
|
|
|
Subsidiary company of Bristol Bay Native Corporation |